Beverly Avenue Project

Beverly Ave Project - Phase 3A

Project Update - May 21, 2019

The Green River Group will continue working on Alley D near the intersection at the bottom of 4th Street. On Monday, May 13 and Tuesday, May 14 the Alley will be closed from 8:00 am – 4:00 p.m. between 4th Street and 5th Street. Plates will be used to cover the trench and allow vehicles down the Alley as needed. There will be a 10-15 minute delay for the contractor to move the plates so resident should expect slight delays. One lane of traffic will be reopened beginning Wednesday, May 15 through Friday, May 17.

On Street Parking will be restricted between 317 and 400 Beverly Ave starting Wednesday, May 22nd at 6:00 A.M. until Friday, May 24th at 5:00 P.M. and then again on Tuesday May 28th and Wednesday 19th.

MUB crews will be working on moving water services from the existing waterline to the new waterline between Fourth St. and Fifth St. on Beverly Ave.The road will be closed during the day between 400 Beverly Ave. and 432 Beverly Ave. Traffic will be accommodated as needed. On-street parking will be closed starting Monday (5/20) at 6:00 A.M. and will remain closed until Friday (5/24) at 5:00 P.M. 

We will provide additional updates as available. Please check back often for updates or sign up for our alert notifications on the top right of this page.

Overview

Beginning March 11, construction will begin on Beverly Avenue and Beverly Alleyway. The expected substantial completion date for this phase of the project is August 9. These dates are dependent on weather and unforseen conditions. As the construction begins, we will try to reduce the impact to residents in the area; however, parking and traffic will be affected. We will update this page frequently with project information including parking and road closures. You can also sign-up by clicking the Beverly Ave Project Alerts title on the right to receive text and email notifications about upcoming parking restrictions, traffic restrictions (i.e. possible changes to one-direction traffic), pedestrian detours and full road closures.

This construction project includes Beverly Avenue, 4th Street, Beverly Alleyway, and the 5th Street Right-of-way between 3rd Street and 6th Street. This streetscape project includes widening and repaving of the roadway, stormwater upgrades, sidewalks and ADA curb ramps, lighting, retaining walls, and dumpster enclosures.

Timeline

  • Pre-Construction Meeting with Contractor, Designer, Utility Companies, and city staff – March 1
  • Construction begins – March 11*
  • WVU Last Day of Class – April 26
  • WVU Graduation – May 10, 11, 12
  • Project Substantial Complete – August 9**
  • First Day of WVU Class – August 21
  • Final Project Acceptance – September 26**

*Dependent on award paperwork finalization
**Dependent on weather and unforeseen conditions

  1. On street parking restricted on Beverly Ave. May 28-29

    On Street Parking will be restricted between 317 and 400 Beverly Ave starting Tuesday, May 28 at 6:00 A.M. until Wednesday, May 29 at 5:00 P.M. Read On...
  2. On Street parking restricted on Beverly Ave. May 22-24

    On Street Parking will be restricted between 317 and 400 Beverly Ave starting Wednesday, May 22nd at 6:00 A.M. until Friday, May 24th at 5:00 P.M. Read On...
  3. On street parking restricted on Beverly Ave. May 20-24

    On street parking will be restricted on Beverly Ave. between 400 Beverly Ave. and 432 Beverly Ave. beginning at 6:00 a.m. Monday, May 20 to 5:00 p.m. Friday, May 24. Read On...
View All

Project Documents